Silver Storm Commences Rehabilitation Activities at La Parrilla
Toronto, Ontario, October 21, 2025: Silver Storm Mining Ltd. (“Silver Storm” or the "Company") (TSX.V: SVRS | OTCQB: SVRS | FSE: SVR) is pleased to announce the Company has commenced rehabilitation activities at its 100%-owned La Parrilla Silver Mine Complex (“La Parrilla”) in Durango State, Mexico.
Highlights:
· Processing Plant Rehabilitation Program has Commenced
o Engineering contractor engaged and mobilized: Dynamic Engineering was awarded the contract for rehabilitation of the La Parrilla processing plant. Estimated completion time is 7 to 9 months.
o Sulphide circuit will be expanded to 1,250 tonnes per day, representing a 25% increase
o Long lead items ordered for processing plant, including flotation cells
· Underground Rehabilitation Work Underway: Initial activities include drift cleaning, scaling, ventilation upgrades, and recommissioning of underground services
· Strategic Restart Plan: SRK Consulting (Canada) has been engaged to review the Company’s restart plan for La Parrilla
“The commencement of rehabilitation activities and the ordering of long-lead items at La Parrilla marks an important milestone for Silver Storm,” stated Greg McKenzie, President & CEO. “With the existing infrastructure in place and recent financings completed, we are taking decisive steps in respect of the Company’s objective of bringing the historic La Parrilla Silver Mine Complex back into production and creating value for our shareholders and the communities of Durango. Rehabilitation and preparation activities will take seven to nine months, and subject to further technical evaluations, we could target the potential restart of operations as early as the second quarter of 2026.”